Uniphar

Project Description

 

The Challenge

  • Uniphar new facility for temperature controlled storage of pharmaceuticals, (Dublin, Ireland)
  • Warehouse area 11,000m³ 15.0m high requiring strict temperature control (15°C to 25°C)
  • Limited available floor space, high level racking throughout
  • Strict budget for installation and lifecycle costs
  • Openly tendered against competing diffusion solutions

 

The Outcome

  • A competitive solution, as compared with other offers, in an open tender competition
  • 3rd party temperature mapping reported a ±1.0°C variance from set point, throughout the 165,000 m³ warehouse (300 sensors)
  • Estimated 30% reduction in heating and cooling costs
  • No air draughts or thermal stratification
  • Stable and homogenous temperature environment for pharmaceuticals

 